Due to the conversion of a Frankfurt coal-fired power plant into a gas-fired power plant, the existing spare parts warehouse had to be dismantled at short notice and the stored goods completely relocated. A replacement building was not yet available. Parallel to the search for rental properties, Rothbaum was to plan the logistics concept and put the individual trades out to tender.
Thanks to Rothbaum’s expertise in warehouse planning and project management, we were able to stabilize the tight schedule and use the project results for rapid implementation.
Dr. Mark Jacquemin, Head of Logistics Department
Mainova AG operates several spare parts warehouses in the Rhine-Main region to ensure the security of supply of gas, electricity, district heating and water to the population. Due to the conversion of a Frankfurt coal-fired power plant into a modern gas-fired power plant, the existing warehouse had to be dismantled. However, in order to restore supplies at short notice in the event of an incident, all spare parts must be available in a central warehouse. A new building was out of the question due to the tight schedule. Rothbaum was therefore commissioned to plan two temporary rental warehouses and to invite tenders for the warehouse equipment (shelving and forklift technology).
Rothbaum worked closely with the Mainova warehouse team to create a planning database with the relevant product range data. Numerous layouts were developed and detailed in joint workshops. The variants were then compared from a technical and economic perspective, the preferred variant was selected and the technical equipment was put out to tender.
Together with the Mainova warehouse team, the master data of the stored goods was enriched and pragmatic assumptions were made in order to obtain a valid database.
Two storage facilities were planned with cantilever, pallet, shelf and floor storage, taking various planning premises into account: Floor load, size of the elevator in the existing building, hall height, fire protection requirements, redundancy and reliability.
Rothbaum drew up a vendor-neutral tender for the logistics equipment on the basis of the Mainova specifications and carried out a technical comparison of the bids received.
The warehouses were occupied in mid-2022 and the warehouse to be dismantled was handed over on time.
Production Manager
Do you have questions about the success story or logistics processes? Or do you have a specific project inquiry? Send me your message and I will get back to you as soon as possible.